PROJECT SCOPE Construction of 100 Dams in Balochistan Project is divided into five Packages to be implemented in seamless continuity.
STRATEGY FOR CONSTRUCTION OF 100 DAMS IN BALOCHISTAN
The Government of Pakistan is sponsoring construction of 100 dams in Balochistan. The Package-I of the project comprising of 20 Dams was launched in June 2009, which has successfully been completed in June 2015. Package-II, comprising of 26 Dams is near completion with physical progress of more than 95%. Package-III of the project comprising of 20 dams is at the anvil of implementation on fast-track basis.
Construction of 100 Dams in Balochistan
Water Sector Project Balochistan - Financed by Federal PSDP
S#
Package No.
No. of Dams
Time Zone
Duration
Achievements/Remarks
1.
Package-I
20 Dams
(2009 to 2014)
5 Years
Completed in June 2015
2.
Package-II
26 Dams
(2013 to 2018)
5 Years
Scheduled to be completed by June 2020
3.
Package-III
20 Dams
(2017 to 2020)
3 Years
Implementation in progress.
4.
Package-IV
23 Dams
(2019 to 2022)
3 Years
PC-I prepared and submitted for approval.
5.
Package-V
11 Dams
(2022 to 2025)
3 Years