100 Dams in Balochistan - All rights reserved.
Name: Location: Approved Cost: Date of Start: Date of Completion: Physical Progress: Financial Progress:
Construction of 100 Dams in Balochistan
Salient Features
Aarah Dam District Awaran Rs. 662.435 million January 2017 December 2019 38% 12%
Type of Dam: Type of Spillway:
Modified Homogenious Earth Fill Dam Ungated Sloping Baffled Appron
TYPE OF DAM
AARAH DAM, DISTRICT AWARAN (PACKAGE-III)
Water Sector Project Balochistan - Financed by Federal PSDP
DAM LOCATION
26° 18' 51.130" N 65° 50' 52.830" E
COORDINATES
Integrated Satellite Map of proposed site