100 Dams in Balochistan - All rights reserved.
Name: Location: Approved Cost: Date of Start: Date of Completion: Physical Progress: Financial Progress:
Construction of 100 Dams in Balochistan
Salient Features
Thank Kuluft Delay Action Dam District Kech (22 kms South East of Hoshab) Rs. 74.066 million January 2013 (Planned) June 2019 50% 50%
64° 06' 39" E, 25° 59' 18" N
Type of Dam: Length: Height: Catchment area: Storage Capacity: Discharge: Type of Spillway: Width: Discharge: Conveyance System: Life of dam:
Modified Homogenious Earth Fill Dam 281.63 Meter 15.24 Meter 25.36 Sq. KM. 1.2 MCM 6250 Cusecs Ungated Sloping Baffled Appron 27.432 Meter 6250 Cusecs 1000 Meter 65 Years
HYDRAULIC DATA
COORDINATES
Integrated Satellite Map of proposed site
THANK KULUFT DAM, DISTRICT KECH (PACKAGE-II)
Location of Thank Kuluft Dam, Kech
26 DAMS LOCATION
Water Sector Project Balochistan - Financed by Federal PSDP