Name: Location: Approved Cost: Date of Start: Date of Completion: Physical Progress: Financial Progress:
Construction of 100 Dams in Balochistan
Salient Features
Lohi Delay Action Dam District Khuzdar (6 kms South of Wadh) Rs. 262.560 million January 2013 (Planned) June 2018 100% 97%
66° 25' 13" E, 27° 17' 29" N
Type of Dam: Length: Height: Catchment area: Storage Capacity: Discharge: Type of Spillway: Width: Discharge: Conveyance System: Life of dam:
Modified Homogenious Earth Fill Dam 213.36 Meter 13.716 Meter 12.72 Sq. KM. 0.74 MCM 6860 Cusecs Ungated Sloping Baffled Appron 29.87 Meter 6860 Cusecs -- 73 Years
HYDRAULIC DATA
COORDINATES
Integrated Satellite Map of proposed site
LOHI DAM, DISTRICT KHUZDAR (PACKAGE-II)
Location of Lohi Dam, Khuzdar
26 DAMS LOCATION
Water Sector Project Balochistan - Financed by Federal PSDP